End item A has a planned lead time of 2 weeks. There are
End item A has a planned lead time of 2 weeks. There are
End item A has a planned lead time of 2 weeks. There are currently 120 units on hand and no scheduled receipts. Compute the planned order releases using lot-for-lot and the Master Production Schedule shown here:Week: 1 -2 – 3 – 4 – 5 – 6 – 7 – 8 – 9 – 10Demand: 41 – 44 – 84 – 42 – 84 – 86 – 7 – 18 – 49 – 30I). Computer number of units on hand for each week.II). Compute net demand for each week.III). Computer planned order receipts for each week.IV). Compute planned order releases for each week.