In the following Table the activities with their precedence
In the following Table the activities with their precedence
In the following Table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl BettertonAc€?cs construction company is working:
Activity
Immediate Predecessor(s)
Time (days)
A
–
3
B
A
4
C
A
6
D
B
6
E
B
4
F
C
4
G
D
6
H
E,F
9
CarlAc€?cs ream should be able to complete the project in – days